| http://www.w3.org/ns/prov#value | - Neither the delays nor the increased costs, however, are particularly material in the context of such a large project with a decade-long construction timeline.The delay, NBN Co???s Mike Quigley says, can be whittled back to an over-run of only six months by the time construction ends in June 2021 rather than at the end of 2020 as originally envisaged.Capital expenditure is forecast to increase by
|