If completion of the Works is delayed as a result of major or unforeseen circumstances, including but not limited to any strike, lock out, shortages of materials, riot, political or civil disturbance, exceptionally inclement weather or any variation, act or omission on the part of the Owner or any other cause beyond the Contractor's control, then: