The key to this project is a plan for how to transition the current LCMP from 72-month operating cycles with 4 major depot availabilities and 14 deployments over a 33-year ship life, to a Block IV and forward plan of 96-month operating cycles with 3 major depot availabilities and 15 deployments over the same ship life.