| http://www.w3.org/ns/prov#value | - on manager, project engineers, process engineer, vice presidents, (Professional Experts) etc from 15 different EPC companies (9 Client companies and 6 Contractor companies).The study reveals that major factors contributing to schedule delay and cost overrun are mostly related to material and equipment such as material shortage, procurement delay, or late delivery on site.
|