| http://www.w3.org/ns/prov#value | - In how many days, working alone, can machine A complete the task?(1) The average time A and B can complete the task working alone is 12.5 days.(2) It would take machine A 5 more days to complete the task alone than it would take for machine B to complete the taskMy answer BTime taken by A alone is a and by B is b.Stmt 1: (a+b)/2= 12.5 => a+b=25. together they complete the task in 6 days => (1/a)+(
|