http://www.w3.org/ns/prov#value | - In other words, if a resource, such as 10 people, is allocated to performing a particular task, called an activity in NST terminology, then the NST assumes that the resource (i.e. the 10 people) is consumed at a constant rate throughout the duration of the task or activity.
|