| http://www.w3.org/ns/prov#value | - We worked for about a year studying the types of systems available (recommended a sequencing batch system over a bio membrane system based on first costs and long term O&M costs), capacity (recommended 1.5 million gallons /day (mgd) capacity for town build out and anticipated commercial activity on Carefree Highway and Cave Creek Road in 20 years, recommended a design-build-operate procurement and
|