| http://www.w3.org/ns/prov#value | - The vessel, due on March 12th, will be in the shipyard for 24 days, work including underwater hull cleaning and painting, refurbishment of three deck cranes and renewal of approximately 40 tonnes of steel in the peak tank, deep tank, wing tank and double bottom tanks
|