| http://www.w3.org/ns/prov#value | - NRS 624.610(1)(d), while seeming to acknowledge two acceptable responses, actually sets out three: 1) issue the change order according to the terms of the request; 2) issue a written objection to the change order request that it is unreasonable and the reasons therefor or 3) issue a written notice to the prime contractor that additional time and/or information is needed to process the change order
|