| http://www.w3.org/ns/prov#value | - Largest volumes required are in the 17 ½??? section and would be displacing hole to mud at section TD. 17 ½??? hole volume = (900 x 0.3415bbls/ft) + (0.2975bbls/ft x 750m) x 3.281 = 1740 bbls based on a rule of thumb that reserve = active requirements.
|